Design basis for coal greenfield plant
The design basis starts with the rock, not the machine. Coal is rated at 10–50 MPa compressive strength with very low abrasiveness, variable moisture sensitivity and a loose bulk density around 0.85 t/m³. Low bulk density flips the usual sizing logic: volume, dust and explosion protection dominate over crusher power. Record the setting before adjusting it, or the baseline is lost.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 220 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of −50 mm and washed size fractions.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Coal · 10–50 MPa · abrasion very low |
| Design throughput | 220 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | −50 mm and washed size fractions |
| Loose bulk density | 0.85 t/m³ |
| Suggested circuit | sizer / impact → screen |

Why long relocation and set-up time appears in this circuit
The plant loses more days to moving and erection than the contract allows. In a coal greenfield plant this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- electrical and conveyor connections differ between modules
- transport permits and axle loads were checked too late
- no written set-up sequence exists for the crew
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) time a full move from stop to first feed; 2) count lifting operations and crane hours; 3) record every connection that needs a tool on site. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For coal at 220 t/h the working train is sizer / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for coal and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~275 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 0.85 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 540 kW order-of-magnitude connected load |
The corrective actions for long relocation and set-up time are applied on top of this base circuit: standardise plug-in connections and conveyor interfaces; verify transport width, height and axle loads before dispatch; write and rehearse a step-by-step set-up checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 40% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Time a full move from stop to first feed
- Count lifting operations and crane hours
- Record every connection that needs a tool on site
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 220 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −50 mm and washed size fractions |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 540 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for coal, while a verifiable mass balance determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 220 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
