Design basis for basalt quarry expansion
The design basis starts with the rock, not the machine. Basalt is rated at 150–300 MPa compressive strength with high abrasiveness, low moisture sensitivity and a loose bulk density around 1.50 t/m³. Very abrasive and tough; wear cost per tonne, not peak throughput, usually decides the circuit and the liner alloy. Record the setting before adjusting it, or the baseline is lost.
A quarry expansion must add saleable output without stopping the existing line, constrained by a shared feed point and limited stockpile area. The commercial priority is throughput continuity. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of railway ballast, 0–5, 5–16, 16–31.5 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Basalt · 150–300 MPa · abrasion high |
| Design throughput | 150 t/h saleable product (150–300 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | railway ballast, 0–5, 5–16, 16–31.5 mm |
| Loose bulk density | 1.50 t/m³ |
| Suggested circuit | jaw → cone → VSI → 3-deck screen |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a basalt quarry expansion this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
A change in one stage changes the circulating load in all the others. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For basalt at 150 t/h the working train is jaw → cone → VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for basalt and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.50 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 370 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 20% and a screen efficiency target above 90%. A change in one stage changes the circulating load in all the others.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast, 0–5, 5–16, 16–31.5 mm |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 370 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for basalt, while throughput continuity determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.