Design basis for gypsum remote site
The design basis starts with the rock, not the machine. Gypsum is rated at 20–60 MPa compressive strength with very low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.25 t/m³. Soft and prone to caking; drying and air-flow control in the grinding circuit matter more than crushing force. Operator notes from the first month are often the best diagnostic data.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of ground powder, 0–10 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gypsum · 20–60 MPa · abrasion very low |
| Design throughput | 100 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | ground powder, 0–10 mm |
| Loose bulk density | 1.25 t/m³ |
| Suggested circuit | impact / hammer → screen → grinding mill |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a gypsum remote site this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For gypsum at 100 t/h the working train is impact / hammer → screen → grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gypsum and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.25 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 300 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 60% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, ground powder, 0–10 mm |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 300 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gypsum, while energy and spares autonomy determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.