Design basis for basalt contract crushing
The design basis starts with the rock, not the machine. Basalt is rated at 150–300 MPa compressive strength with high abrasiveness, low moisture sensitivity and a loose bulk density around 1.50 t/m³. Very abrasive and tough; wear cost per tonne, not peak throughput, usually decides the circuit and the liner alloy. A change in one stage changes the circulating load in all the others.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of railway ballast, 0–5, 5–16, 16–31.5 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Basalt · 150–300 MPa · abrasion high |
| Design throughput | 100 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | railway ballast, 0–5, 5–16, 16–31.5 mm |
| Loose bulk density | 1.50 t/m³ |
| Suggested circuit | jaw → cone → VSI → 3-deck screen |

Why capacity shortfall appears in this circuit
The line stabilises at 70–85% of its quoted throughput. In a basalt contract crushing this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.
- the mass balance was sized for fresh feed without circulating load
- a feeder or conveyor reaches its volumetric limit before the crusher does
- screen efficiency falls as near-size material builds up in the return loop
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) weigh the return belt over a full shift; 2) log crusher power draw against feeder rate; 3) sieve the screen oversize for near-size content. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For basalt at 100 t/h the working train is jaw → cone → VSI → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for basalt and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.50 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 250 kW order-of-magnitude connected load |
The corrective actions for capacity shortfall are applied on top of this base circuit: recalculate the full mass balance including the return stream; add surge capacity ahead of the secondary stage to hold choke feed; resize the limiting conveyor or screen deck rather than the crusher.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 40% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Weigh the return belt over a full shift
- Log crusher power draw against feeder rate
- Sieve the screen oversize for near-size content
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast, 0–5, 5–16, 16–31.5 mm |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 250 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for basalt, while mobility and fast set-up determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.