Design basis for andesite contract crushing
The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. Indicative values are starting points for a design, not guarantees.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 80 t/h of saleable product, with a maximum feed top size near 300 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Andesite · 120–240 MPa · abrasion medium–high |
| Design throughput | 80 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~300 mm |
| Target product | asphalt aggregate, 0–5, 5–16 mm |
| Loose bulk density | 1.44 t/m³ |
| Suggested circuit | jaw → cone → VSI → screen |

Why capacity shortfall appears in this circuit
The line stabilises at 70–85% of its quoted throughput. In a andesite contract crushing this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- the mass balance was sized for fresh feed without circulating load
- a feeder or conveyor reaches its volumetric limit before the crusher does
- screen efficiency falls as near-size material builds up in the return loop
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) weigh the return belt over a full shift; 2) log crusher power draw against feeder rate; 3) sieve the screen oversize for near-size content. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For andesite at 80 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~100 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.44 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 260 kW order-of-magnitude connected load |
The corrective actions for capacity shortfall are applied on top of this base circuit: recalculate the full mass balance including the return stream; add surge capacity ahead of the secondary stage to hold choke feed; resize the limiting conveyor or screen deck rather than the crusher.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 20% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Weigh the return belt over a full shift
- Log crusher power draw against feeder rate
- Sieve the screen oversize for near-size content
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 80 t/h nominal |
| Grading | Full sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 260 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while mobility and fast set-up determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 80 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.