Design basis for andesite quarry expansion
The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. A change in one stage changes the circulating load in all the others.
A quarry expansion must add saleable output without stopping the existing line, constrained by a shared feed point and limited stockpile area. The commercial priority is throughput continuity. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Andesite · 120–240 MPa · abrasion medium–high |
| Design throughput | 150 t/h saleable product (150–300 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | asphalt aggregate, 0–5, 5–16 mm |
| Loose bulk density | 1.44 t/m³ |
| Suggested circuit | jaw → cone → VSI → screen |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a andesite quarry expansion this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For andesite at 150 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.44 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 370 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 20% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 370 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while throughput continuity determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.