Overview
A practical Construction waste crushing plant configuration by capacity, with the equipment list and screening setup that HAMAC typically specifies.

30–100 t/h
- Primary jaw (PE series).
- Secondary impact or small cone.
- 2-deck screen for 2–3 products.
- Wheel or tracked for mobility.
100–300 t/h
- Primary jaw + secondary cone.
- 3-deck screen, multiple fractions.
- Dust control and conveyors.
- Stationary or modular.
300–800 t/h
- Large jaw or gyratory primary.
- Two-stage cone train.
- Multiple screens and stockpiles.
- PLC control, full dust suppression.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Construction waste |
| Mohs hardness | 3 |
| Compressive strength | ~60 MPa |
| Abrasiveness | Low |
| Recommended circuit | mobile jaw + impact + screen |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on construction waste crushing; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for construction waste crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a coastal export terminal in mind before fixing conveyor lengths.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Apply mobile jaw + impact + screen; the reduction mechanism must suit low abrasion and a compressive strength near 60 MPa.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for your market.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Product sampling points and the lab equipment needed for routine grading checks.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Dust and noise control designed to the local emission limits for your market.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Decommissioning or relocation value at the end of a five-year horizon.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 55% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
For demolition and recycling duties, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify rotation direction on every motor before coupling.
- Measure and log the as-new CSS / setting for future wear comparison.
- Dry-run the plant empty for the specified period and record vibration.
- Confirm the direction and tension of every belt under no load.
- Check lubrication levels, grease lines and oil cooler operation.
- Test emergency stops, pull wires and interlock trips in sequence.
The commissioning record becomes the reference for every liner change in the five-year plan.