Overview
A practical Gypsum crushing plant configuration by capacity, with the equipment list and screening setup that HAMAC typically specifies.

30–100 t/h
- Primary jaw (PE series).
- Secondary impact or small cone.
- 2-deck screen for 2–3 products.
- Wheel or tracked for mobility.
100–300 t/h
- Primary jaw + secondary cone.
- 3-deck screen, multiple fractions.
- Dust control and conveyors.
- Stationary or modular.
300–800 t/h
- Large jaw or gyratory primary.
- Two-stage cone train.
- Multiple screens and stockpiles.
- PLC control, full dust suppression.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Gypsum |
| Mohs hardness | 1.5 |
| Compressive strength | ~30 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and three-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | strict product cubicity |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for gypsum crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against Gypsum (Mohs 1.5, ~30 MPa, low abrasion).
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Product sampling points and the lab equipment needed for routine grading checks.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Wear-part interchangeability across machines in the same circuit.
Ask each supplier to price the same list. Quotations for gypsum crushing only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 55% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 13% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For gypsum crushing at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in your market until erection has already started.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying strict product cubicity on price alone and losing it in availability.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm all guards, emergency stops and pull-wire switches function.
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
On an existing quarry bench, allow extra time for the dust and noise measurements.