Overview
A 100–200 tph crushing plant is a common size for Zambia. Main machines: PE/PEW jaw + cone + 3-deck screen. Most common export plant size.

Main equipment
- PE/PEW jaw + cone + 3-deck screen
- Shipped to Dar es Salaam.
- Configured to 380V 50Hz / ZS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Zambia
- Port: Dar es Salaam.
- Voltage: 380V 50Hz.
- Standards: ZS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Destination port | Dar es Salaam |
| Site supply | 380V 50Hz |
| Local standards | ZS |
| Region | Africa |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | ten-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | minimal civil works |
| Evaluation horizon | ten-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Lay out the PE/PEW jaw + cone + 3-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
A realistic programme reserves time for permits, foundation curing and shipping to Zambia before any steel is cut.

What to verify before you sign
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Local service partner, technician travel time and visa requirements for Zambia.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Nameplate data for 380V 50Hz and the ZS certificate set.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Product sampling points and the lab equipment needed for routine grading checks.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm the direction and tension of every belt under no load.
- Measure noise and dust at the operator position against the local limit.
- Check belt tracking, chute build-up and transfer-point dust.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Confirm all guards, emergency stops and pull-wire switches function.
Keep the signed record; it is the only defensible baseline for later performance disputes.