Overview
Published Crawler (Tracked) Impact Crusher TF Series specifications below are nominal values transcribed from HAMAC data. Actual performance depends on feed gradation, moisture, setting and screening efficiency.

Specification table
| Parameter | Value |
|---|---|
| Impact crusher | LF150 LF250 |
| Max. feeding size | 500 mm 700 mm |
| Capacity | 100–200 t/h 200–400 t/h |
| Motor power | 90–200 kW 180–250 kW |
| Return screen | 2YK1530 2YS1640 |
| Generator | 360 kW 500 kW |
How to read the data
- Rated capacity is at a specified CSS / setting and material — treat it as saleable product, not crusher throughput.
- Feed size limit protects the chamber; oversize feed causes bridging.
- Motor power scales with rotor / chamber size, not linearly with capacity.
Selecting the right model
Match the model to your target t/h at the required product size, then confirm with a HAMAC engineer before order.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Crawler (Tracked) Impact Crusher TF Series |
| Category | Tracked Crushing Plants |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | three-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Published Crawler (Tracked) Impact Crusher TF Series model data
| Model | TF150 | TF250 | TF350 |
|---|---|---|---|
| Impact crusher | LF150 | LF250 | LF350 |
| Max. feeding size | 500 mm | 700 mm | 800 mm |
| Capacity | 100–200 t/h | 200–400 t/h | 300–500 t/h |
| Motor power | 90–200 kW | 180–250 kW | 200–400 kW |
| Return screen | 2YK1530 | 2YS1640 | YS1740 |
| Generator | 360 kW | 500 kW | 520 kW |
TF150 / TF250 / TF350 tracked impact crushers, 100–500 t/h, ideal for limestone, concrete and asphalt recycling. Read the table column by column against cement raw-meal preparation: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | three-year view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for crawler (tracked) impact crusher tf series may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Closed-side setting range and whether automatic setting regulation is included.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
For cement raw-meal preparation, give the lowest cost per tonne line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On cement raw-meal preparation, the lowest cost per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Using one liner profile for both secondary and tertiary stages.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
On a confined urban yard, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Record power draw, tonnage and chamber pressure at steady state.
- Sample each product fraction and compare with the specification.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm the direction and tension of every belt under no load.
- Check lubrication levels, grease lines and oil cooler operation.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm all guards, emergency stops and pull-wire switches function.
Keep the signed record; it is the only defensible baseline for later performance disputes.