Overview
Wear parts are the largest variable cost on a KJ Series Modular Crushing & Screening Plant. HAMAC supplies matched consumables and a recommended stock list with every plant.

Main consumables
- Chamber liners / blow bars / Impact plates.
- Rotors, distributor plates and anvils (VSI).
- Screen meshes for every deck.
- Belts, bearings, seals and sensors.
Liner material grade
Mn13 / Mn18 / Mn22 work-harden under impact; high-chrome resists abrasion in low-impact duties. Choice follows the rock, not the price.
Recommended stock
- One full set of chamber liners or blow bars.
- Screen meshes for every deck.
- Belts, bearings and seals.
- Electrical consumables and sensors.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | KJ Series Modular Crushing & Screening Plant |
| Category | Modular Crushing Plant |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | ten-year view |
At demolition and recycling duties, the ranking of these parameters changes: minimal civil works usually becomes the deciding constraint rather than the headline tonnage.
Published KJ Series Modular Crushing & Screening Plant model data
| Plant type | Model | Standard device | Vehicle-mounted device | Capacity (t/h) | Transport dimensions (mm) |
|---|---|---|---|---|---|
| Jaw crusher plant | KJ98 | GZDT9538 | HDX98 | 90–350 | 12750 × 3020 × 3850 |
| Jaw crusher plant | KJ110 | GZDT1145B | HDX110 | 120–450 | 13050 × 3050 × 4000 |
| Impact crusher plant | KJ1213 | GZDT9538 | C11213 | 80–320 | 12970 × 3020 × 3920 |
| Impact crusher plant | KJ1316 | GZDT1145B | C11316 | 100–400 | 13290 × 3050 × 4080 |
| Cone crusher plant | K1300 | — | HPM300C1 | 60–280 | 15650 × 3270 × 3780 |
| Cone crusher plant | KJ250 | — | SC250F1 | 90–350 | 15600 × 3270 × 3800 |
| Sand maker plant | KJ0926 | — | HVI0926 | 85–240 | 15400 × 2770 × 3780 |
| Sand maker plant | KJ1040 | — | HVI1040 | 120–284 | 15400 × 2920 × 3970 |
KJ modular stations for jaw, impact, cone, VSI sand making and screening, 60–500 t/h, with foundation-free installation and transportable dimensions. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | minimal civil works |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for kj series modular crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
Shortening this sequence is possible on a brownfield extension, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Wear-part interchangeability across machines in the same circuit.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Local service partner, technician travel time and visa requirements for your market.
- Control system language, telemetry and remote diagnostics availability.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Energy draw in kW and the expected kWh per tonne at the design duty.
Ask each supplier to price the same list. Quotations for kj series modular crushing & screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On demolition and recycling duties, the minimal civil works objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Buying minimal civil works on price alone and losing it in availability.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Record power draw, tonnage and chamber pressure at steady state.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
The commissioning record becomes the reference for every liner change in the ten-year plan.