Overview
The European Tech. Jaw Crusher is offered across several model sizes. Price depends on capacity, wear-package grade, mobility (stationary, wheel or tracked) and the level of automation, not on a single list price.

What drives the price
- Model size and rated capacity — larger rotors / chambers cost more.
- Mobility: stationary < wheel-mounted < tracked (tracked adds hydraulic & engine cost).
- Motor specification and starter (soft-start / VFD) and local voltage.
- Wear-parts grade (Mn13 / Mn18 / Mn22 / high-chrome) and spare-parts package.
- Control system: relay panel vs PLC with remote monitoring.
Typical price brackets
Entry models for contractor use start in the low five-figure USD range; mid-size export configurations are typically six-figure; large tracked or fully automated lines are higher. Exact numbers depend on the technical specification — request a written quotation rather than a ballpark.
How to get an accurate quote
Send material, feed size, target t/h and product sizes. HAMAC returns a flow sheet, equipment list and FOB / CFR / CIF price within 24 hours.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | European Tech. Jaw Crusher |
| Category | Jaw Crusher |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | ten-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Published European Tech. Jaw Crusher model data
| Model | Feed opening | Motor Power | Rotation speed | Jaw plate length | Max single part weight | Total weight |
|---|---|---|---|---|---|---|
| 6CX80 | 800×510 mm | 75 kW | 350 rpm | 1100 mm | 2870 kg | 7520 kg |
| 6CX96 | 930×580 mm | 75(90) kW | 300 rpm | 1380 mm | 4500 kg | 12000 kg |
| 6CX106 | 1060×700 mm | 110 kW | 280 rpm | 1450 mm | 7800 kg | 19000 kg |
| 6CX110 | 1100×850 mm | 132(160) kW | 230 rpm | 1800 mm | 9000 kg | 25060 kg |
| 6CX125 | 1250×950 mm | 160(132) kW | 220 rpm | 2000 mm | 12960 kg | 36700 kg |
| 6CX140 | 1400×1070 mm | 200(160) kW | 220 rpm | 2100 mm | 15950 kg | 45300 kg |
| 6CX145 | 1400×1100 mm | 200 kW | 220 rpm | 2300 mm | 18600 kg | 53800 kg |
| 6CX160 | 1600×1200 mm | 250(200) kW | 220 rpm | 2500 mm | 21380 kg | 68600 kg |
The European Tech. jaw crusher, developed using advanced international crushing technology, is designed for high-efficiency crushing of hard, abrasive materials. Read the table column by column against cement raw-meal preparation: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | ten-year view |
| Site condition | a greenfield site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for european tech. jaw crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Dust and noise control designed to the local emission limits for your market.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Product sampling points and the lab equipment needed for routine grading checks.
- Local service partner, technician travel time and visa requirements for your market.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the cement raw-meal preparation duty be defined verbally instead of in the contract.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Calibrate the belt scale and any level probes against a known load.
- Verify rotation direction on every motor before coupling.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Record the baseline grading curve for each product fraction.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
For a mixed local and expatriate team, run through this list twice — once with the supervisor and once without.