Choosing a Tracked Cone Crusher Plant starts with the rock and the target product, not a catalogue number. The steps below turn your project data into a defensible model choice.

1. Start with the material
- Hard, abrasive rock (granite, basalt, quartz): compression crushing, premium Mn liners.
- Soft rock (limestone, marble, dolomite): impact crushing for shape at lower cost.
- High silica (river pebble, quartz): plan VSI + wear budget.
2. Size to saleable t/h
Add 10–20% surge to nameplate capacity; undersizing is a permanent bottleneck, oversizing wastes capital.
3. Match the product grading
Product size and shape (flakiness index) decide chamber and screen deck setup.
Pre-order checklist
- Feed size and max lump.
- Required t/h and product fractions.
- Site power (voltage / frequency) and mobility need.
- Local standards (CE, GOST, etc.).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Tracked Cone Crusher Plant |
| Category | Tracked Crushing Plants |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for tracked cone crusher plant cannot be compared on scope.
Published Tracked Cone Crusher Plant model data
| Model | MC200HRSE | MC300HRE | MC300HRSE | MC400HRSE |
|---|---|---|---|---|
| Feeder | ||||
| Volume(m³) | 6.5 | 6.5 | 6.5 | 6.5 |
| Feeding height(mm) | 2900 | 2870 | 2900 | 2560 |
| Maximum feed size(mm) | 185 | 225 | 225 | 275 |
| Feeding capacity(t/h) | 400 | 500 | 500 | 700 |
| Crusher | ||||
| Host model | HPC200 | HPC300 | HPC300 | HPC400 |
| Return screen length×width(mm) | 1740x5000 | 1740x5000 | 1740x5000 | 1800x5000 |
Maximize your productivity with the versatile Tracked Cone Crusher Plant! Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for an existing quarry bench in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | minimal civil works |
| Evaluation horizon | five-year view |
| Site condition | an existing quarry bench |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for tracked cone crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.

From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.
What to verify before you sign
- Control system language, telemetry and remote diagnostics availability.
- Local service partner, technician travel time and visa requirements for your market.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Guaranteed power draw and the minimal civil works trade-off it implies.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Closed-side setting range and whether automatic setting regulation is included.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the five-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For tracked cone crusher plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check lubrication levels, grease lines and oil cooler operation.
On an existing quarry bench, allow extra time for the dust and noise measurements.