Overview
Choosing a Crawler (Tracked) Cone Crusher THP Series starts with the rock and the target product, not a catalogue number. The steps below turn your project data into a defensible model choice.

1. Start with the material
- Hard, abrasive rock (granite, basalt, quartz): compression crushing, premium Mn liners.
- Soft rock (limestone, marble, dolomite): impact crushing for shape at lower cost.
- High silica (river pebble, quartz): plan VSI + wear budget.
2. Size to saleable t/h
Add 10–20% surge to nameplate capacity; undersizing is a permanent bottleneck, oversizing wastes capital.
3. Match the product grading
Product size and shape (flakiness index) decide chamber and screen deck setup.
Pre-order checklist
- Feed size and max lump.
- Required t/h and product fractions.
- Site power (voltage / frequency) and mobility need.
- Local standards (CE, GOST, etc.).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Crawler (Tracked) Cone Crusher THP Series |
| Category | Tracked Crushing Plants |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | three-year view |
Use the table as a checklist when comparing quotations for crawler (tracked) cone crusher thp series — a lower price often means one of these parameters was quietly reduced.
Published Crawler (Tracked) Cone Crusher THP Series model data
| Model | THP200 | THP300 | THP400 |
|---|---|---|---|
| Cone crusher | THP200 | THP300 | THP400 |
| Max. feeding size | 150 mm | 200 mm | 260 mm |
| Minimum outlet | 16 mm | 10 mm | 20 mm |
| Motor power | 160 kW | 220 kW | 280 kW |
| Return screen | YK1500×3800 | YK1600×4000 | YK1500×3800 |
| Generator | 320 kW | 500 kW | 500 kW |
THP200 / THP300 / THP400 tracked cone crushers for secondary hard-rock crushing, 150–260 mm feed and 160–280 kW crusher power. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for an existing quarry bench in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | simple operator maintenance |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for crawler (tracked) cone crusher thp series may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.

From enquiry to the first saleable tonne
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.
What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Dust and noise control designed to the local emission limits for your market.
- Local service partner, technician travel time and visa requirements for your market.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Control system language, telemetry and remote diagnostics availability.
- Decommissioning or relocation value at the end of a three-year horizon.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping a geotechnical check and discovering settlement under the primary crusher at an existing quarry bench.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
For demolition and recycling duties, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check lubrication levels, grease lines and oil cooler operation.
- Measure and log the as-new CSS / setting for future wear comparison.
- Sample each product fraction and compare with the specification.
- Measure noise and dust at the operator position against the local limit.
- Verify rotation direction on every motor before coupling.
On an existing quarry bench, allow extra time for the dust and noise measurements.