Overview
Quartz (Mohs 7, ~150 MPa, high abrasion): processing steps, equipment and cost notes for plant buyers.

Processing steps
- Primary crushing — jaw.
- Secondary / tertiary — jaw + cone + VSI.
- Screening for graded products.
- Dewatering / handling.
Recommended equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
Cost notes
Operating cost is dominated by wear parts on high-abrasion material; choose liner grade by rock, not price.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Quartz |
| Mohs hardness | 7 |
| Compressive strength | ~150 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone + VSI |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | ten-year view |
The figures above are transcribed from published HAMAC data and from the material properties of quartz; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | fast mobilisation |
| Evaluation horizon | ten-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for quartz crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Written performance guarantee, sampling method and acceptance-test protocol.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Wear-part interchangeability across machines in the same circuit.
- Guaranteed power draw and the fast mobilisation trade-off it implies.
- Liner alloy: Mn22 is a common starting point for quartz at high abrasion.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 18% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Confirm the direction and tension of every belt under no load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Check lubrication levels, grease lines and oil cooler operation.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Record the baseline grading curve for each product fraction.
Keep the signed record; it is the only defensible baseline for later performance disputes.