Overview
Practical, numbers-first guidance on the Compound Cone Crusher — written for engineers specifying, buying and running crushing plants.

Capacity factors
- Chamber / CSS and material.
- Feed gradation and moisture.
- Screen efficiency downstream.
- Continuous vs surge feed.
Rule of thumb
Rated capacity is stated at a given CSS and material; treat it as saleable product, not crusher throughput. Size the plant to 10–20% above target.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Compound Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | three-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and three-year operating plan.
Published Compound Cone Crusher model data
| Model | Cavity Type | Stroke | Feed Limit | Exit Aperture | Capacity | Motor Power | Weight |
|---|---|---|---|---|---|---|---|
| HMC1650C2-D | Coarse | 34 mm | 300 mm | 35-65 mm | 280-610 t/h | 250 kw | 35 t |
| HMC1650C-D | Coarse | 34 mm | 260 mm | 30-60 mm | 265-580 t/h | 250 kw | 35 t |
| HMC1650Z-D | Medium Coarse | 34 mm | 240 mm | 25-60 mm | 240-550 t/h | 250 kw | 35 t |
| HMC1650S-X | Fine | 28 mm | 130 mm | 20-45 mm | 180-350 t/h | 250 kw | 35 t |
| HMC1400C-D | Coarse | 30 mm | 235 mm | 30-60 mm | 210-530 t/h | 220 kw | 25 t |
| HMC1400Z-D | Medium Coarse | 30 mm | 215 mm | 25-50 mm | 200-500 t/h | 220 kw | 25 t |
| HMC1400Z-X | Medium Coarse | 25 mm | 180 mm | 22-45 mm | 180-475 t/h | 220 kw | 25 t |
| HMC1400S-X | Fine | 25 mm | 100 mm | 19-40 mm | 130-260 t/h | 220 kw | 25 t |
HMC series compound spring cone crusher is a more convenient cone crusher which is researched on the base of traditional spring cone crusher. Read the table column by column against high-tonnage aggregate supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | fast mobilisation |
| Evaluation horizon | three-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for compound cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Review the crusher chamber profile with the liner supplier against the feed material.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Closed-side setting range and whether automatic setting regulation is included.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Decommissioning or relocation value at the end of a three-year horizon.
- Local service partner, technician travel time and visa requirements for your market.
For high-tonnage aggregate supply, give the fast mobilisation line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Buying fast mobilisation on price alone and losing it in availability.
Review the list with a full-time plant team before the order is placed — they will recognise most of them.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check belt tracking, chute build-up and transfer-point dust.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Hand over the spare-parts list, manuals and maintenance schedule.
The commissioning record becomes the reference for every liner change in the three-year plan.