Overview
A turnkey contract covers the flow sheet, manufacture, shipment to Yokohama, civil reference drawings, erection supervision, commissioning and operator training — one project manager from enquiry to hand-over.

Scope of supply
- Site survey and material testing.
- Flow sheet, layout and foundation reference.
- Manufacture, workshop assembly and load test.
- Freight and customs documentation for Japan.
- Erection supervision, 200V 50/60Hz power tie-in and training.
Market parameters for Japan
| Item | Reference |
|---|---|
| Region | Asia |
| Port | Yokohama |
| Voltage / frequency | 200V 50/60Hz |
| Standards | JIS |
| Typical feed | Granite, Limestone |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Yokohama |
| Site supply | 200V 50/60Hz |
| Local standards | JIS |
| Region | Asia |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
For a mixed local and expatriate team, the commissioning and training steps need more calendar time than the mechanical erection itself.
What to verify before you sign
- Guaranteed power draw and the lowest cost per tonne trade-off it implies.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Local service partner, technician travel time and visa requirements for Japan.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
- Confirm the direction and tension of every belt under no load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure and log the as-new CSS / setting for future wear comparison.
The commissioning record becomes the reference for every liner change in the ten-year plan.