Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Japan, from quotation to commissioning.

Shipping & port
- Destination: Yokohama.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 200V 50/60Hz.
- Standards: JIS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Japan customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Yokohama |
| Site supply | 200V 50/60Hz |
| Local standards | JIS |
| Region | Asia |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | tight grading compliance |
| Evaluation horizon | five-year view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Japan.

What to verify before you sign
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Nameplate data for 200V 50/60Hz and the JIS certificate set.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On mine pre-beneficiation feed, the tight grading compliance objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
- Sample each product fraction and compare with the specification.
- Check lubrication levels, grease lines and oil cooler operation.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Record power draw, tonnage and chamber pressure at steady state.
- Hand over the spare-parts list, manuals and maintenance schedule.
On a brownfield extension, allow extra time for the dust and noise measurements.