Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Ethiopia, from quotation to commissioning.

Shipping & port
- Destination: Djibouti.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 380V 50Hz.
- Standards: ES.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Ethiopia customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Djibouti |
| Site supply | 380V 50Hz |
| Local standards | ES |
| Region | Africa |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Book container or flat-rack space to Djibouti and prepare the customs document set in advance.
- Specify motors, starters and documentation for 380V 50Hz and ES before manufacture.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Decommissioning or relocation value at the end of a five-year horizon.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Control system language, telemetry and remote diagnostics availability.
- Wear-part interchangeability across machines in the same circuit.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Dust and noise control designed to the local emission limits for Ethiopia.
- Nameplate data for 380V 50Hz and the ES certificate set.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Using one liner profile for both secondary and tertiary stages.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Overlooking dust, noise and water permits in Ethiopia until erection has already started.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure noise and dust at the operator position against the local limit.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check belt tracking, chute build-up and transfer-point dust.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Verify rotation direction on every motor before coupling.
- Test emergency stops, pull wires and interlock trips in sequence.
For a rotating shift crew, run through this list twice — once with the supervisor and once without.