Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Kenya, from quotation to commissioning.

Shipping & port
- Destination: Mombasa.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 415V 50Hz.
- Standards: KS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Kenya customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mombasa |
| Site supply | 415V 50Hz |
| Local standards | KS |
| Region | Africa |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | three-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | minimal civil works |
| Evaluation horizon | three-year view |
| Site condition | a greenfield site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Specify motors, starters and documentation for 415V 50Hz and KS before manufacture.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Whether the quoted t/h is achieved at cement raw-meal preparation or under ideal laboratory feed.
- Guaranteed power draw and the minimal civil works trade-off it implies.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Local service partner, technician travel time and visa requirements for Kenya.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Product sampling points and the lab equipment needed for routine grading checks.
- Closed-side setting range and whether automatic setting regulation is included.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the three-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Letting the cement raw-meal preparation duty be defined verbally instead of in the contract.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Buying minimal civil works on price alone and losing it in availability.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check belt tracking, chute build-up and transfer-point dust.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure noise and dust at the operator position against the local limit.
- Record the baseline grading curve for each product fraction.
- Calibrate the belt scale and any level probes against a known load.
For a small contractor crew, run through this list twice — once with the supervisor and once without.