Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Fiji, from quotation to commissioning.

Shipping & port
- Destination: Suva.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 400V 50Hz.
- Standards: FNS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Fiji customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Suva |
| Site supply | 400V 50Hz |
| Local standards | FNS |
| Region | Oceania |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | five-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Book container or flat-rack space to Suva and prepare the customs document set in advance.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
- Decommissioning or relocation value at the end of a five-year horizon.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Nameplate data for 400V 50Hz and the FNS certificate set.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Buying lowest energy per tonne on price alone and losing it in availability.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check belt tracking, chute build-up and transfer-point dust.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Calibrate the belt scale and any level probes against a known load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm the direction and tension of every belt under no load.
Keep the signed record; it is the only defensible baseline for later performance disputes.