Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Zambia, from quotation to commissioning.

Shipping & port
- Destination: Dar es Salaam.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 380V 50Hz.
- Standards: ZS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Zambia customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Dar es Salaam |
| Site supply | 380V 50Hz |
| Local standards | ZS |
| Region | Africa |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Wear-part interchangeability across machines in the same circuit.
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
- Nameplate data for 380V 50Hz and the ZS certificate set.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Dust and noise control designed to the local emission limits for Zambia.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in Zambia until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Sample each product fraction and compare with the specification.
- Measure noise and dust at the operator position against the local limit.
- Dry-run the plant empty for the specified period and record vibration.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
On a coastal export terminal, allow extra time for the dust and noise measurements.