Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Sri Lanka, from quotation to commissioning.

Shipping & port
- Destination: Colombo.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 400V 50Hz.
- Standards: SLS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Sri Lanka customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Colombo |
| Site supply | 400V 50Hz |
| Local standards | SLS |
| Region | Asia |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | three-year view |
Treat this as a living sheet. Every revision of the flow sheet for Sri Lanka should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | tight grading compliance |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Wear-part interchangeability across machines in the same circuit.
- Product sampling points and the lab equipment needed for routine grading checks.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Nameplate data for 400V 50Hz and the SLS certificate set.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A three-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Sample each product fraction and compare with the specification.
- Check belt tracking, chute build-up and transfer-point dust.
- Calibrate the belt scale and any level probes against a known load.
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
On an existing quarry bench, allow extra time for the dust and noise measurements.