Overview
HAMAC supplies crushing and grinding equipment to Saudi Arabia, shipped to Jeddah and quoted to local standards (SASO). Power is configured for 380V 60Hz.

Crushing equipment for Saudi Arabia
- Popular material: Limestone, Gabbro.
- Destination port: Jeddah.
- Voltage / frequency: 380V 60Hz.
- Standards: SASO.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 380V 60Hz and SASO.
- FOB / CFR / CIF quotation to Jeddah.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Saudi Arabia, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Jeddah |
| Site supply | 380V 60Hz |
| Local standards | SASO |
| Region | Middle East |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | five-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and five-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | strict product cubicity |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Book container or flat-rack space to Jeddah and prepare the customs document set in advance.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Local service partner, technician travel time and visa requirements for Saudi Arabia.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Nameplate data for 380V 60Hz and the SASO certificate set.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Whether the quoted t/h is achieved at high-tonnage aggregate supply or under ideal laboratory feed.
- Closed-side setting range and whether automatic setting regulation is included.
- Wear-part interchangeability across machines in the same circuit.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Letting the high-tonnage aggregate supply duty be defined verbally instead of in the contract.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Overlooking dust, noise and water permits in Saudi Arabia until erection has already started.
- Comparing quotations with different port terms and calling the lower number cheaper.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Verify rotation direction on every motor before coupling.
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record the baseline grading curve for each product fraction.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure noise and dust at the operator position against the local limit.
- Dry-run the plant empty for the specified period and record vibration.
On a greenfield site, allow extra time for the dust and noise measurements.