Overview
HAMAC supplies crushing and grinding equipment to Bangladesh, shipped to Chittagong and quoted to local standards (BSTI). Power is configured for 400V 50Hz.

Crushing equipment for Bangladesh
- Popular material: Limestone, Aggregates.
- Destination port: Chittagong.
- Voltage / frequency: 400V 50Hz.
- Standards: BSTI.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 400V 50Hz and BSTI.
- FOB / CFR / CIF quotation to Chittagong.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Bangladesh, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Chittagong |
| Site supply | 400V 50Hz |
| Local standards | BSTI |
| Region | Asia |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | three-year view |
Treat this as a living sheet. Every revision of the flow sheet for Bangladesh should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | three-year view |
| Site condition | a coastal export terminal |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Written performance guarantee, sampling method and acceptance-test protocol.
- Control system language, telemetry and remote diagnostics availability.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Energy draw in kW and the expected kWh per tonne at the design duty.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A three-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Buying lowest energy per tonne on price alone and losing it in availability.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Using one liner profile for both secondary and tertiary stages.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Verify rotation direction on every motor before coupling.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record power draw, tonnage and chamber pressure at steady state.
For a small contractor crew, run through this list twice — once with the supervisor and once without.