Overview
A under 50 tph plant for gypsum (Mohs 1.5, ~30 MPa, low abrasion). Recommended circuit: jaw + impact.

Gypsum at this scale
| Capacity | 10–50 t/h |
|---|---|
| Material | Gypsum (Low abrasion) |
| Circuit | jaw + impact |
Equipment
- PE Series Jaw Crusher
- PF Impact Crusher
- Vibrating Feeder
Notes
Soft; gentle crushing for board grade, then grinding.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Gypsum |
| Mohs hardness | 1.5 |
| Compressive strength | ~30 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Design capacity | 10–50 t/h |
| Typical main line | small jaw + impact/cone, skid or mobile |
| Scale note | Contractor and pilot scale, fast set-up. |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | three-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and three-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for gypsum crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Survey the feed: Gypsum (Mohs 1.5, ~30 MPa, low abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Liner alloy: high-chrome iron is a common starting point for gypsum at low abrasion.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Closed-side setting range and whether automatic setting regulation is included.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Ask each supplier to price the same list. Quotations for gypsum crushing only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For gypsum crushing at 10–50 t/h, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 10–50 t/h.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Dry-run the plant empty for the specified period and record vibration.
- Sample each product fraction and compare with the specification.
- Record the baseline grading curve for each product fraction.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Calibrate the belt scale and any level probes against a known load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
For a small contractor crew, run through this list twice — once with the supervisor and once without.