Overview
A 200–300 tph crushing plant is a common size for Spain. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Main equipment
- large jaw + 2× cone + screens
- Shipped to Valencia.
- Configured to 400V 50Hz / UNE EN.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Spain
- Port: Valencia.
- Voltage: 400V 50Hz.
- Standards: UNE EN.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Destination port | Valencia |
| Site supply | 400V 50Hz |
| Local standards | UNE EN |
| Region | Europe |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | fast mobilisation |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Lay out the large jaw + 2× cone + screens arrangement with straight conveyor runs and crane access for liner changes.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
On cement raw-meal preparation, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Control system language, telemetry and remote diagnostics availability.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Wear-part interchangeability across machines in the same circuit.
- Whether the quoted t/h is achieved at cement raw-meal preparation or under ideal laboratory feed.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Dust and noise control designed to the local emission limits for Spain.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
Share this list with a full-time plant team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On cement raw-meal preparation, the fast mobilisation objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Buying fast mobilisation on price alone and losing it in availability.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm the direction and tension of every belt under no load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
Keep the signed record; it is the only defensible baseline for later performance disputes.