Overview
A 50–100 tph crushing plant is a common size for Myanmar. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Main equipment
- PE jaw + PF impact / cone + 2-deck screen
- Shipped to Yangon.
- Configured to 380V 50Hz / MSS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Myanmar
- Port: Yangon.
- Voltage: 380V 50Hz.
- Standards: MSS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Destination port | Yangon |
| Site supply | 380V 50Hz |
| Local standards | MSS |
| Region | Asia |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | ten-year view |
Treat this as a living sheet. Every revision of the flow sheet for Myanmar should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | strict product cubicity |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Lay out the PE jaw + PF impact / cone + 2-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Size the primary stage for 50–100 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Myanmar.

What to verify before you sign
- Wear-part interchangeability across machines in the same circuit.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Closed-side setting range and whether automatic setting regulation is included.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Dust and noise control designed to the local emission limits for Myanmar.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping a geotechnical check and discovering settlement under the primary crusher at an existing quarry bench.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 50–100 t/h.
For demolition and recycling duties, protect the strict product cubicity requirement explicitly in the contract documents.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Record power draw, tonnage and chamber pressure at steady state.
- Sample each product fraction and compare with the specification.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
Keep the signed record; it is the only defensible baseline for later performance disputes.