Overview
A 300–500 tph plant for gabbro (Mohs 6, ~180 MPa, high abrasion). Recommended circuit: jaw + cone.

Gabbro at this scale
| Capacity | 300–500 t/h |
|---|---|
| Material | Gabbro (High abrasion) |
| Circuit | jaw + cone |
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
Notes
Massive, abrasive; premium liners.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Gabbro |
| Mohs hardness | 6 |
| Compressive strength | ~180 MPa |
| Abrasiveness | High |
| Recommended circuit | jaw + cone |
| Design capacity | 300–500 t/h |
| Typical main line | primary gyratory/jaw + cone train |
| Scale note | Commercial aggregate production. |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | seven-year view |
The figures above are transcribed from published HAMAC data and from the material properties of gabbro; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for gabbro crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Apply jaw + cone; the reduction mechanism must suit high abrasion and a compressive strength near 180 MPa.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Size the primary stage for 300–500 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
A HAMAC project manager stays with the order from the first data sheet through hand-over in your market.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Liner alloy: Mn13 is a common starting point for gabbro at high abrasion.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 19% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 300–500 t/h.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
On a confined urban yard, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Check lubrication levels, grease lines and oil cooler operation.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
- Check belt tracking, chute build-up and transfer-point dust.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Verify rotation direction on every motor before coupling.
On a confined urban yard, allow extra time for the dust and noise measurements.