Overview
A 300–500 tph crushing plant is a common size for India. Main machines: primary gyratory/jaw + cone train. Commercial aggregate production.

Main equipment
- primary gyratory/jaw + cone train
- Shipped to Mumbai.
- Configured to 415V 50Hz / BIS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For India
- Port: Mumbai.
- Voltage: 415V 50Hz.
- Standards: BIS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 300–500 t/h |
| Typical main line | primary gyratory/jaw + cone train |
| Scale note | Commercial aggregate production. |
| Destination port | Mumbai |
| Site supply | 415V 50Hz |
| Local standards | BIS |
| Region | Asia |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | single-project view |
At high-tonnage aggregate supply, the ranking of these parameters changes: tight grading compliance usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | tight grading compliance |
| Evaluation horizon | single-project view |
| Site condition | a confined urban yard |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out the primary gyratory/jaw + cone train arrangement with straight conveyor runs and crane access for liner changes.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Specify motors, starters and documentation for 415V 50Hz and BIS before manufacture.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Decommissioning or relocation value at the end of a single-project horizon.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Guaranteed power draw and the tight grading compliance trade-off it implies.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Control system language, telemetry and remote diagnostics availability.
- Whether the quoted t/h is achieved at high-tonnage aggregate supply or under ideal laboratory feed.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
A single-project view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches 300–500 t/h.
- Buying tight grading compliance on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
On a confined urban yard, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record the baseline grading curve for each product fraction.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure noise and dust at the operator position against the local limit.
- Record power draw, tonnage and chamber pressure at steady state.
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm all guards, emergency stops and pull-wire switches function.
Keep the signed record; it is the only defensible baseline for later performance disputes.