Overview
This page brings together the published VSI Vertical Shaft Impact Crusher (Sand Making Machine) model data and the practical details of importing it into Vietnam — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Granite.

Published VSI Vertical Shaft Impact Crusher (Sand Making Machine) data
| Published parameter | Nominal value |
|---|---|
| VSI7611 | ≤35 60–90 |
| VSI7615 | ≤35 70–140 |
| VSI8518 | ≤40 100–130 |
| VSI8522 | ≤40 120–160 |
| VSI9526 | ≤45 150–190 |
| VSI9532 | ≤45 180–220 |
Local conditions in Vietnam
- Destination port: Ho Chi Minh.
- Site supply: 380V 50Hz.
- Standards: TCVN.
- Common materials: Limestone, Granite.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Ho Chi Minh, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to TCVN. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Ho Chi Minh |
| Site supply | 380V 50Hz |
| Local standards | TCVN |
| Region | Asia |
| Machine line | VSI Vertical Shaft Impact Crusher (Sand Making Machine) |
| Category | Sand Making & Washing |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Published VSI Vertical Shaft Impact Crusher (Sand Making Machine) model data
| Model | Max. feeding size (mm) | Nominal through capacity (t/h) | Motor power (kW) |
|---|---|---|---|
| VSI7611 | ≤35 | 60–90 | 55×2 |
| VSI7615 | ≤35 | 70–140 | 75×2 |
| VSI8518 | ≤40 | 100–130 | 90×2 |
| VSI8522 | ≤40 | 120–160 | 110×2 |
| VSI9526 | ≤45 | 150–190 | 132×2 |
| VSI9532 | ≤45 | 180–220 | 160×2 |
| VSI1140 | ≤50 | 225–260 | 200×2 |
| VSI1145 | ≤50 | 250–300 | 220×2 |
VSI sand making machine, 60–500 t/h, for manufactured sand and aggregate shaping with rock-on-rock crushing and interchangeable wear parts. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | strict product cubicity |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for vsi vertical shaft impact crusher (sand making machine) may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Book container or flat-rack space to Ho Chi Minh and prepare the customs document set in advance.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Local service partner, technician travel time and visa requirements for Vietnam.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Control system language, telemetry and remote diagnostics availability.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Share this list with an owner-operator team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Buying strict product cubicity on price alone and losing it in availability.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Overlooking dust, noise and water permits in Vietnam until erection has already started.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Verify rotation direction on every motor before coupling.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
- Check belt tracking, chute build-up and transfer-point dust.
The commissioning record becomes the reference for every liner change in the ten-year plan.