Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Germany — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Recycling.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Germany
- Destination port: Hamburg.
- Site supply: 400V 50Hz.
- Standards: DIN EN.
- Common materials: Limestone, Recycling.
- Region: Europe.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Hamburg, sets motors and starters to 400V 50Hz, and supplies the certificate set applicable to DIN EN. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Hamburg |
| Site supply | 400V 50Hz |
| Local standards | DIN EN |
| Region | Europe |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on mobile jaw crusher plant; they are nominal and should be confirmed against a sample test before manufacture.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Book container or flat-rack space to Hamburg and prepare the customs document set in advance.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Specify motors, starters and documentation for 400V 50Hz and DIN EN before manufacture.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
Shortening this sequence is possible on a confined urban yard, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Written performance guarantee, sampling method and acceptance-test protocol.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Nameplate data for 400V 50Hz and the DIN EN certificate set.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the five-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Using one liner profile for both secondary and tertiary stages.
- Overlooking dust, noise and water permits in Germany until erection has already started.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
For mine pre-beneficiation feed, protect the lowest energy per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check lubrication levels, grease lines and oil cooler operation.
- Record the baseline grading curve for each product fraction.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Test emergency stops, pull wires and interlock trips in sequence.
- Hand over the spare-parts list, manuals and maintenance schedule.
The commissioning record becomes the reference for every liner change in the five-year plan.