Overview
This page brings together the published HPT Multi-Cylinder Hydraulic Cone Crusher model data and the practical details of importing it into Pakistan — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Coal.

Published HPT Multi-Cylinder Hydraulic Cone Crusher data
| Published parameter | Nominal value |
|---|---|
| HPT100 | 90 45–140 |
| HPT200 | 160 90–250 |
| HPT300 | 220 110–440 |
| HPT400 / HPT500 | On request On request |
Local conditions in Pakistan
- Destination port: Karachi.
- Site supply: 400V 50Hz.
- Standards: PSQCA.
- Common materials: Limestone, Coal.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Karachi, sets motors and starters to 400V 50Hz, and supplies the certificate set applicable to PSQCA. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Karachi |
| Site supply | 400V 50Hz |
| Local standards | PSQCA |
| Region | Asia |
| Machine line | HPT Multi-Cylinder Hydraulic Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for hpt multi-cylinder hydraulic cone crusher — a lower price often means one of these parameters was quietly reduced.
Published HPT Multi-Cylinder Hydraulic Cone Crusher model data
| Model | Installed power (kW) | Capacity range (t/h) | Dimensions (mm) |
|---|---|---|---|
| HPT100 | 90 | 45–140 | 1705 × 1510 × 1583 |
| HPT200 | 160 | 90–250 | 2135 × 1750 × 1927 |
| HPT300 | 220 | 110–440 | 2725 × 2110 × 2871 |
| HPT400 / HPT500 | On request | On request | On request |
Hydraulic multi-cylinder cone crusher for secondary and tertiary crushing of limestone through basalt, with 5–15% higher efficiency and 35–60% higher output than spring cone crushers. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | fast mobilisation |
| Evaluation horizon | ten-year view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for hpt multi-cylinder hydraulic cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Control system language, telemetry and remote diagnostics availability.
- Nameplate data for 400V 50Hz and the PSQCA certificate set.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Closed-side setting range and whether automatic setting regulation is included.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
Share this list with an owner-operator team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Using one liner profile for both secondary and tertiary stages.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Dry-run the plant empty for the specified period and record vibration.
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm the direction and tension of every belt under no load.
- Measure and log the as-new CSS / setting for future wear comparison.
The commissioning record becomes the reference for every liner change in the ten-year plan.