Overview
This page brings together the published PF Impact Crusher model data and the practical details of importing it into Malaysia — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Granite.

Published PF Impact Crusher data
| Published parameter | Nominal value |
|---|---|
| PF-1007 | Φ1000×700 mm 400×730 mm |
| PF-1010 | Φ1000×1050 mm 400×1080 mm |
| PF-1210 | Φ1250×1050 mm 400×1080 mm |
| PF-1214 | Φ1250×1400 mm 400×1430 mm |
| PF-1315 | Φ1320×1500 mm 860×1520 mm |
| PF-1520 | Φ1500×2000 mm 830×2040 mm |
Local conditions in Malaysia
- Destination port: Port Klang.
- Site supply: 415V 50Hz.
- Standards: SIRIM.
- Common materials: Limestone, Granite.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Port Klang, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to SIRIM. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Port Klang |
| Site supply | 415V 50Hz |
| Local standards | SIRIM |
| Region | Asia |
| Machine line | PF Impact Crusher |
| Category | Impact Crusher |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | single-project view |
At manufactured-sand production, the ranking of these parameters changes: tight grading compliance usually becomes the deciding constraint rather than the headline tonnage.
Published PF Impact Crusher model data
| Model | Rotor size | Feed opening | Max. Feeding size | Capacity | Motor Power | Weight | Overall dimension |
|---|---|---|---|---|---|---|---|
| PF-1007 | Φ1000×700 mm | 400×730 mm | 300 mm | 30-70 t/h | 37-45 kW | 12 t | 2330×1660×2300 mm |
| PF-1010 | Φ1000×1050 mm | 400×1080 mm | 350 mm | 50-90 t/h | 45-55 kW | 15 t | 2370×1700×2390 mm |
| PF-1210 | Φ1250×1050 mm | 400×1080 mm | 350 mm | 70-130 t/h | 110 kW | 17.7 t | 2680×2160×2800 mm |
| PF-1214 | Φ1250×1400 mm | 400×1430 mm | 350 mm | 100-180 t/h | 132 kW | 22.4 t | 2650×2460×2800 mm |
| PF-1315 | Φ1320×1500 mm | 860×1520 mm | 500 mm | 130-250 t/h | 220 kW | 27 t | 3180×2720×2620 mm |
| PF-1520 | Φ1500×2000 mm | 830×2040 mm | 700 mm | 300-550 t/h | 315-400 kW | 50.6 t | 3959×3564×3330 mm |
| PF-1620 | Φ1600×2000 mm | 2000×1600 mm | 500 mm | 400-700 t/h | 400-500 kW | 58 t | 4259×3660×3450 mm |
| PF-1820 | Φ1800×2000 mm | 1260×2040 mm | 800 mm | 600-800 t/h | 630-710 kW | 83.21 t | 4400×3866×4009 mm |
The impact crusher (impact crusher) is a new generation of impact crusher developed in combination with the specific working conditions of the sand and gravel. Read the table column by column against manufactured-sand production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | tight grading compliance |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for pf impact crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Book container or flat-rack space to Port Klang and prepare the customs document set in advance.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
On manufactured-sand production, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Decommissioning or relocation value at the end of a single-project horizon.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Guaranteed power draw and the tight grading compliance trade-off it implies.
- Control system language, telemetry and remote diagnostics availability.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Written performance guarantee, sampling method and acceptance-test protocol.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the single-project review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Overlooking dust, noise and water permits in Malaysia until erection has already started.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Using one liner profile for both secondary and tertiary stages.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
On a remote mine site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Test emergency stops, pull wires and interlock trips in sequence.
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify rotation direction on every motor before coupling.
- Check belt tracking, chute build-up and transfer-point dust.
- Record the baseline grading curve for each product fraction.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
For a full-time plant team, run through this list twice — once with the supervisor and once without.