Overview
This page brings together the published PF Impact Crusher model data and the practical details of importing it into Kenya — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Basalt.

Published PF Impact Crusher data
| Published parameter | Nominal value |
|---|---|
| PF-1007 | Φ1000×700 mm 400×730 mm |
| PF-1010 | Φ1000×1050 mm 400×1080 mm |
| PF-1210 | Φ1250×1050 mm 400×1080 mm |
| PF-1214 | Φ1250×1400 mm 400×1430 mm |
| PF-1315 | Φ1320×1500 mm 860×1520 mm |
| PF-1520 | Φ1500×2000 mm 830×2040 mm |
Local conditions in Kenya
- Destination port: Mombasa.
- Site supply: 415V 50Hz.
- Standards: KS.
- Common materials: Limestone, Basalt.
- Region: Africa.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Mombasa, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to KS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mombasa |
| Site supply | 415V 50Hz |
| Local standards | KS |
| Region | Africa |
| Machine line | PF Impact Crusher |
| Category | Impact Crusher |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | seven-year view |
Ask for the same table from any competing supplier; without it, an offer for pf impact crusher cannot be compared on scope.
Published PF Impact Crusher model data
| Model | Rotor size | Feed opening | Max. Feeding size | Capacity | Motor Power | Weight | Overall dimension |
|---|---|---|---|---|---|---|---|
| PF-1007 | Φ1000×700 mm | 400×730 mm | 300 mm | 30-70 t/h | 37-45 kW | 12 t | 2330×1660×2300 mm |
| PF-1010 | Φ1000×1050 mm | 400×1080 mm | 350 mm | 50-90 t/h | 45-55 kW | 15 t | 2370×1700×2390 mm |
| PF-1210 | Φ1250×1050 mm | 400×1080 mm | 350 mm | 70-130 t/h | 110 kW | 17.7 t | 2680×2160×2800 mm |
| PF-1214 | Φ1250×1400 mm | 400×1430 mm | 350 mm | 100-180 t/h | 132 kW | 22.4 t | 2650×2460×2800 mm |
| PF-1315 | Φ1320×1500 mm | 860×1520 mm | 500 mm | 130-250 t/h | 220 kW | 27 t | 3180×2720×2620 mm |
| PF-1520 | Φ1500×2000 mm | 830×2040 mm | 700 mm | 300-550 t/h | 315-400 kW | 50.6 t | 3959×3564×3330 mm |
| PF-1620 | Φ1600×2000 mm | 2000×1600 mm | 500 mm | 400-700 t/h | 400-500 kW | 58 t | 4259×3660×3450 mm |
| PF-1820 | Φ1800×2000 mm | 1260×2040 mm | 800 mm | 600-800 t/h | 630-710 kW | 83.21 t | 4400×3866×4009 mm |
The impact crusher (impact crusher) is a new generation of impact crusher developed in combination with the specific working conditions of the sand and gravel. Read the table column by column against demolition and recycling duties: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | strict product cubicity |
| Evaluation horizon | seven-year view |
| Site condition | a remote mine site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for pf impact crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Book container or flat-rack space to Mombasa and prepare the customs document set in advance.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Control system language, telemetry and remote diagnostics availability.
- Local service partner, technician travel time and visa requirements for Kenya.
Ask each supplier to price the same list. Quotations for pf impact crusher only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Letting the demolition and recycling duties duty be defined verbally instead of in the contract.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Using one liner profile for both secondary and tertiary stages.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
For demolition and recycling duties, protect the strict product cubicity requirement explicitly in the contract documents.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Sample each product fraction and compare with the specification.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Measure and log the as-new CSS / setting for future wear comparison.
- Dry-run the plant empty for the specified period and record vibration.
- Record power draw, tonnage and chamber pressure at steady state.
- Hand over the spare-parts list, manuals and maintenance schedule.
Keep the signed record; it is the only defensible baseline for later performance disputes.