Overview
A turnkey contract covers the flow sheet, manufacture, shipment to Dar es Salaam, civil reference drawings, erection supervision, commissioning and operator training — one project manager from enquiry to hand-over.

Scope of supply
- Site survey and material testing.
- Flow sheet, layout and foundation reference.
- Manufacture, workshop assembly and load test.
- Freight and customs documentation for Zambia.
- Erection supervision, 380V 50Hz power tie-in and training.
Market parameters for Zambia
| Item | Reference |
|---|---|
| Region | Africa |
| Port | Dar es Salaam |
| Voltage / frequency | 380V 50Hz |
| Standards | ZS |
| Typical feed | Copper ore, Cobalt |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Dar es Salaam |
| Site supply | 380V 50Hz |
| Local standards | ZS |
| Region | Africa |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | three-year view |
Treat this as a living sheet. Every revision of the flow sheet for Zambia should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | minimal civil works |
| Evaluation horizon | three-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Specify motors, starters and documentation for 380V 50Hz and ZS before manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Review the crusher chamber profile with the liner supplier against the feed material.
Shortening this sequence is possible on a coastal export terminal, but only where the feed and product specification are already fully defined.
What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Local service partner, technician travel time and visa requirements for Zambia.
- Decommissioning or relocation value at the end of a three-year horizon.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Control system language, telemetry and remote diagnostics availability.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Guaranteed power draw and the minimal civil works trade-off it implies.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the three-year review.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On contract crushing on short-term sites, the minimal civil works objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a coastal export terminal.
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Assuming the manufacturer's warranty covers wear parts and consumables.
On a coastal export terminal, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure noise and dust at the operator position against the local limit.
- Verify rotation direction on every motor before coupling.
- Measure and log the as-new CSS / setting for future wear comparison.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
On a coastal export terminal, allow extra time for the dust and noise measurements.