Overview
This page brings together the published HPT Multi-Cylinder Hydraulic Cone Crusher model data and the practical details of importing it into Kenya — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Basalt.

Published HPT Multi-Cylinder Hydraulic Cone Crusher data
| Published parameter | Nominal value |
|---|---|
| HPT100 | 90 45–140 |
| HPT200 | 160 90–250 |
| HPT300 | 220 110–440 |
| HPT400 / HPT500 | On request On request |
Local conditions in Kenya
- Destination port: Mombasa.
- Site supply: 415V 50Hz.
- Standards: KS.
- Common materials: Limestone, Basalt.
- Region: Africa.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Mombasa, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to KS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mombasa |
| Site supply | 415V 50Hz |
| Local standards | KS |
| Region | Africa |
| Machine line | HPT Multi-Cylinder Hydraulic Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Published HPT Multi-Cylinder Hydraulic Cone Crusher model data
| Model | Installed power (kW) | Capacity range (t/h) | Dimensions (mm) |
|---|---|---|---|
| HPT100 | 90 | 45–140 | 1705 × 1510 × 1583 |
| HPT200 | 160 | 90–250 | 2135 × 1750 × 1927 |
| HPT300 | 220 | 110–440 | 2725 × 2110 × 2871 |
| HPT400 / HPT500 | On request | On request | On request |
Hydraulic multi-cylinder cone crusher for secondary and tertiary crushing of limestone through basalt, with 5–15% higher efficiency and 35–60% higher output than spring cone crushers. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for hpt multi-cylinder hydraulic cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Book container or flat-rack space to Mombasa and prepare the customs document set in advance.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
For a full-time plant team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Control system language, telemetry and remote diagnostics availability.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Product sampling points and the lab equipment needed for routine grading checks.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Dust and noise control designed to the local emission limits for Kenya.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
Share this list with a full-time plant team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
For contract crushing on short-term sites, protect the lowest cost per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify rotation direction on every motor before coupling.
Keep the signed record; it is the only defensible baseline for later performance disputes.