Overview
This page brings together the published HPT Multi-Cylinder Hydraulic Cone Crusher model data and the practical details of importing it into Algeria — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Aggregates.

Published HPT Multi-Cylinder Hydraulic Cone Crusher data
| Published parameter | Nominal value |
|---|---|
| HPT100 | 90 45–140 |
| HPT200 | 160 90–250 |
| HPT300 | 220 110–440 |
| HPT400 / HPT500 | On request On request |
Local conditions in Algeria
- Destination port: Algiers.
- Site supply: 380V 50Hz.
- Standards: NA.
- Common materials: Limestone, Aggregates.
- Region: Africa.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Algiers, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to NA. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Algiers |
| Site supply | 380V 50Hz |
| Local standards | NA |
| Region | Africa |
| Machine line | HPT Multi-Cylinder Hydraulic Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | continuous quarry production |
| Evaluation horizon | ten-year view |
Ask for the same table from any competing supplier; without it, an offer for hpt multi-cylinder hydraulic cone crusher cannot be compared on scope.
Published HPT Multi-Cylinder Hydraulic Cone Crusher model data
| Model | Installed power (kW) | Capacity range (t/h) | Dimensions (mm) |
|---|---|---|---|
| HPT100 | 90 | 45–140 | 1705 × 1510 × 1583 |
| HPT200 | 160 | 90–250 | 2135 × 1750 × 1927 |
| HPT300 | 220 | 110–440 | 2725 × 2110 × 2871 |
| HPT400 / HPT500 | On request | On request | On request |
Hydraulic multi-cylinder cone crusher for secondary and tertiary crushing of limestone through basalt, with 5–15% higher efficiency and 35–60% higher output than spring cone crushers. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for an existing quarry bench in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | tight grading compliance |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for hpt multi-cylinder hydraulic cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Book container or flat-rack space to Algiers and prepare the customs document set in advance.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
Shortening this sequence is possible on an existing quarry bench, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Nameplate data for 380V 50Hz and the NA certificate set.
- Guaranteed power draw and the tight grading compliance trade-off it implies.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Dust and noise control designed to the local emission limits for Algeria.
Ask each supplier to price the same list. Quotations for hpt multi-cylinder hydraulic cone crusher only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Skipping a geotechnical check and discovering settlement under the primary crusher at an existing quarry bench.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Comparing quotations with different port terms and calling the lower number cheaper.
For continuous quarry production, protect the tight grading compliance requirement explicitly in the contract documents.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Check belt tracking, chute build-up and transfer-point dust.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
For a full-time plant team, run through this list twice — once with the supervisor and once without.