Overview
Limestone (Mohs 3, ~100 MPa) is processed in Ethiopia for aggregates, ore or industrial minerals. HAMAC configures the circuit to local conditions: Djibouti, 380V 50Hz, ES.

Limestone properties
| Property | Value |
|---|---|
| Mohs | 3 |
| Compressive strength | 100 MPa |
| Abrasion | Low |
| Circuit | jaw + impact |
In Ethiopia
- Port: Djibouti.
- Power: 380V 50Hz.
- Standards: ES.
Equipment
- PE Series Jaw Crusher
- PF Impact Crusher
- Mobile Impact Crusher Plant
Budget
Send material, capacity and product sizes for a configured FOB/CIF budget to Djibouti.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Limestone |
| Mohs hardness | 3 |
| Compressive strength | ~100 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Destination port | Djibouti |
| Site supply | 380V 50Hz |
| Local standards | ES |
| Region | Africa |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | three-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | three-year view |
| Site condition | an existing quarry bench |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for limestone crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Survey the feed: Limestone (Mohs 3, ~100 MPa, low abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Apply jaw + impact; the reduction mechanism must suit low abrasion and a compressive strength near 100 MPa.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Product sampling points and the lab equipment needed for routine grading checks.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Control system language, telemetry and remote diagnostics availability.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Liner alloy: Mn18 with ceramic inserts is a common starting point for limestone at low abrasion.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Wear-part interchangeability across machines in the same circuit.
For seasonal road-project supply, give the lowest cost per tonne line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For limestone crushing at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Using one liner profile for both secondary and tertiary stages.
For seasonal road-project supply, protect the lowest cost per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Calibrate the belt scale and any level probes against a known load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify rotation direction on every motor before coupling.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure and log the as-new CSS / setting for future wear comparison.
The commissioning record becomes the reference for every liner change in the three-year plan.