Overview
A 300–500 tph plant for dolomite (Mohs 3.5, ~110 MPa, low abrasion). Recommended circuit: jaw + impact.

Dolomite at this scale
| Capacity | 300–500 t/h |
|---|---|
| Material | Dolomite (Low abrasion) |
| Circuit | jaw + impact |
Equipment
- PE Series Jaw Crusher
- PF Impact Crusher
Notes
Flux stone and aggregate.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Dolomite |
| Mohs hardness | 3.5 |
| Compressive strength | ~110 MPa |
| Abrasiveness | Low |
| Recommended circuit | jaw + impact |
| Design capacity | 300–500 t/h |
| Typical main line | primary gyratory/jaw + cone train |
| Scale note | Commercial aggregate production. |
| Assumed duty | continuous quarry production |
| Evaluation horizon | seven-year view |
At continuous quarry production, the ranking of these parameters changes: simple operator maintenance usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for dolomite crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Survey the feed: Dolomite (Mohs 3.5, ~110 MPa, low abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Dust and noise control designed to the local emission limits for your market.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Liner alloy: Mn22 is a common starting point for dolomite at low abrasion.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
For continuous quarry production, give the simple operator maintenance line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 52% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 17% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
For continuous quarry production, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm all guards, emergency stops and pull-wire switches function.
- Record power draw, tonnage and chamber pressure at steady state.
- Calibrate the belt scale and any level probes against a known load.
Keep the signed record; it is the only defensible baseline for later performance disputes.