Overview
Construction aggregate is the largest crusher market; graded fractions must meet local road standards. In Saudi Arabia the most frequently processed feed materials are Limestone, Gabbro, and equipment is normally delivered through Jeddah on 380V 60Hz supplies.

Materials in scope
- Granite — Mohs 6.5, ~180 MPa, high abrasion
- Limestone — Mohs 3, ~100 MPa, low abrasion
- Basalt — Mohs 6, ~200 MPa, high abrasion
Recommended machines
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
- PF Impact Crusher
- Mobile Impact Crusher Plant
Engineering for Saudi Arabia
| Item | Reference |
|---|---|
| Port | Jeddah |
| Power | 380V 60Hz |
| Standards | SASO |
| Region | Middle East |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Jeddah |
| Site supply | 380V 60Hz |
| Local standards | SASO |
| Region | Middle East |
| Application | Aggregates & Quarry |
| Typical feed | Granite, Limestone, Basalt |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | single-project view |
Treat this as a living sheet. Every revision of the flow sheet for Saudi Arabia should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | single-project view |
| Site condition | a greenfield site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Saudi Arabia.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Closed-side setting range and whether automatic setting regulation is included.
- Guaranteed power draw and the lowest energy per tonne trade-off it implies.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On manufactured-sand production, the lowest energy per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Comparing quotations with different port terms and calling the lower number cheaper.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Record the baseline grading curve for each product fraction.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Measure and log the as-new CSS / setting for future wear comparison.
On a greenfield site, allow extra time for the dust and noise measurements.