Overview
Single-size, high-PSV, low-flakiness aggregate. In Indonesia the most frequently processed feed materials are Coal, Limestone, Nickel, and equipment is normally delivered through Tanjung Priok on 380V 50Hz supplies.

Materials in scope
- Basalt — Mohs 6, ~200 MPa, high abrasion
- Granite — Mohs 6.5, ~180 MPa, high abrasion
- Andesite — Mohs 6, ~170 MPa, high abrasion
Recommended machines
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
Engineering for Indonesia
| Item | Reference |
|---|---|
| Port | Tanjung Priok |
| Power | 380V 50Hz |
| Standards | SNI |
| Region | Asia |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Tanjung Priok |
| Site supply | 380V 50Hz |
| Local standards | SNI |
| Region | Asia |
| Application | Road & Railway Ballast |
| Typical feed | Basalt, Granite, Andesite |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | single-project view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Specify motors, starters and documentation for 380V 50Hz and SNI before manufacture.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Indonesia.

What to verify before you sign
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Decommissioning or relocation value at the end of a single-project horizon.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Control system language, telemetry and remote diagnostics availability.
- Dust and noise control designed to the local emission limits for Indonesia.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Comparing quotations with different port terms and calling the lower number cheaper.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Confirm the direction and tension of every belt under no load.
- Check belt tracking, chute build-up and transfer-point dust.
- Verify rotation direction on every motor before coupling.
- Test emergency stops, pull wires and interlock trips in sequence.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Dry-run the plant empty for the specified period and record vibration.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
Keep the signed record; it is the only defensible baseline for later performance disputes.