Overview
A 500–800 tph crushing plant is a common size for Philippines. Main machines: dual primary + multi-cone. Large quarry / mine feed.

Main equipment
- dual primary + multi-cone
- Shipped to Manila.
- Configured to 380V 60Hz / PNS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Philippines
- Port: Manila.
- Voltage: 380V 60Hz.
- Standards: PNS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 500–800 t/h |
| Typical main line | dual primary + multi-cone |
| Scale note | Large quarry / mine feed. |
| Destination port | Manila |
| Site supply | 380V 60Hz |
| Local standards | PNS |
| Region | Asia |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | three-year view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out the dual primary + multi-cone arrangement with straight conveyor runs and crane access for liner changes.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Control system language, telemetry and remote diagnostics availability.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Nameplate data for 380V 60Hz and the PNS certificate set.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Buying lowest energy per tonne on price alone and losing it in availability.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Overlooking dust, noise and water permits in Philippines until erection has already started.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
For manufactured-sand production, protect the lowest energy per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm the direction and tension of every belt under no load.
- Dry-run the plant empty for the specified period and record vibration.
- Calibrate the belt scale and any level probes against a known load.
- Measure and log the as-new CSS / setting for future wear comparison.
- Test emergency stops, pull wires and interlock trips in sequence.
On a confined urban yard, allow extra time for the dust and noise measurements.