Overview
A 100–200 tph plant for copper ore (Mohs 4, ~120 MPa, medium abrasion). Recommended circuit: jaw + cone.

Copper ore at this scale
| Capacity | 100–200 t/h |
|---|---|
| Material | Copper ore (Medium abrasion) |
| Circuit | jaw + cone |
Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
Notes
Crushed then ground for flotation / SX-EW.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Feed material | Copper ore |
| Mohs hardness | 4 |
| Compressive strength | ~120 MPa |
| Abrasiveness | Medium |
| Recommended circuit | jaw + cone |
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | ten-year view |
Treat this as a living sheet. Every revision of the flow sheet for your market should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for copper ore crushing may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Survey the feed: Copper ore (Mohs 4, ~120 MPa, medium abrasion); record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Apply jaw + cone; the reduction mechanism must suit medium abrasion and a compressive strength near 120 MPa.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Size the primary stage for 100–200 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
A HAMAC project manager stays with the order from the first data sheet through hand-over in your market.

What to verify before you sign
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Guaranteed power draw and the lowest cost per tonne trade-off it implies.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 9% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 17% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a medium-abrasion feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping a geotechnical check and discovering settlement under the primary crusher at an existing quarry bench.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Calibrate the belt scale and any level probes against a known load.
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Dry-run the plant empty for the specified period and record vibration.
- Check lubrication levels, grease lines and oil cooler operation.
- Measure noise and dust at the operator position against the local limit.
The commissioning record becomes the reference for every liner change in the ten-year plan.