Overview
A 200–300 tph crushing plant is a common size for Ethiopia. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Main equipment
- large jaw + 2× cone + screens
- Shipped to Djibouti.
- Configured to 380V 50Hz / ES.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Ethiopia
- Port: Djibouti.
- Voltage: 380V 50Hz.
- Standards: ES.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Destination port | Djibouti |
| Site supply | 380V 50Hz |
| Local standards | ES |
| Region | Africa |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | single-project view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and single-project operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 200–300 t/h.
- Whether the quoted t/h is achieved at seasonal road-project supply or under ideal laboratory feed.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the single-project review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Overlooking dust, noise and water permits in Ethiopia until erection has already started.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check lubrication levels, grease lines and oil cooler operation.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Record the baseline grading curve for each product fraction.
- Test emergency stops, pull wires and interlock trips in sequence.
The commissioning record becomes the reference for every liner change in the single-project plan.