Overview
A 200–300 tph crushing plant is a common size for Australia. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Main equipment
- large jaw + 2× cone + screens
- Shipped to Sydney.
- Configured to 415V 50Hz / AS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Australia
- Port: Sydney.
- Voltage: 415V 50Hz.
- Standards: AS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Destination port | Sydney |
| Site supply | 415V 50Hz |
| Local standards | AS |
| Region | Oceania |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | seven-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Lay out the large jaw + 2× cone + screens arrangement with straight conveyor runs and crane access for liner changes.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Size the primary stage for 200–300 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Book container or flat-rack space to Sydney and prepare the customs document set in advance.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Australia.

What to verify before you sign
- Decommissioning or relocation value at the end of a seven-year horizon.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
- Nameplate data for 415V 50Hz and the AS certificate set.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the seven-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Overlooking dust, noise and water permits in Australia until erection has already started.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Dry-run the plant empty for the specified period and record vibration.
- Measure noise and dust at the operator position against the local limit.
- Check belt tracking, chute build-up and transfer-point dust.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check lubrication levels, grease lines and oil cooler operation.
- Record the baseline grading curve for each product fraction.
- Verify rotation direction on every motor before coupling.
On a brownfield extension, allow extra time for the dust and noise measurements.