Overview
A 50–100 tph crushing plant is a common size for Angola. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Main equipment
- PE jaw + PF impact / cone + 2-deck screen
- Shipped to Luanda.
- Configured to 380V 50Hz / NA.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Angola
- Port: Luanda.
- Voltage: 380V 50Hz.
- Standards: NA.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Destination port | Luanda |
| Site supply | 380V 50Hz |
| Local standards | NA |
| Region | Africa |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | three-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | minimal civil works |
| Evaluation horizon | three-year view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Specify motors, starters and documentation for 380V 50Hz and NA before manufacture.
- Lay out the PE jaw + PF impact / cone + 2-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Product sampling points and the lab equipment needed for routine grading checks.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Control system language, telemetry and remote diagnostics availability.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Wear-part interchangeability across machines in the same circuit.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at 50–100 t/h, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Overlooking dust, noise and water permits in Angola until erection has already started.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming the manufacturer's warranty covers wear parts and consumables.
On a remote mine site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Record power draw, tonnage and chamber pressure at steady state.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Measure noise and dust at the operator position against the local limit.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Hand over the spare-parts list, manuals and maintenance schedule.
Keep the signed record; it is the only defensible baseline for later performance disputes.