Overview
A 100–200 tph crushing plant is a common size for Turkey. Main machines: PE/PEW jaw + cone + 3-deck screen. Most common export plant size.

Main equipment
- PE/PEW jaw + cone + 3-deck screen
- Shipped to Istanbul.
- Configured to 380V 50Hz / TS EN.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Turkey
- Port: Istanbul.
- Voltage: 380V 50Hz.
- Standards: TS EN.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Destination port | Istanbul |
| Site supply | 380V 50Hz |
| Local standards | TS EN |
| Region | Europe/Asia |
| Assumed duty | continuous quarry production |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Specify motors, starters and documentation for 380V 50Hz and TS EN before manufacture.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Size the primary stage for 100–200 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Closed-side setting range and whether automatic setting regulation is included.
- Product sampling points and the lab equipment needed for routine grading checks.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
For continuous quarry production, give the maximum mechanical availability line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Overlooking dust, noise and water permits in Turkey until erection has already started.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
For continuous quarry production, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Confirm the direction and tension of every belt under no load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Calibrate the belt scale and any level probes against a known load.
- Record power draw, tonnage and chamber pressure at steady state.
- Check lubrication levels, grease lines and oil cooler operation.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm all guards, emergency stops and pull-wire switches function.
For a full-time plant team, run through this list twice — once with the supervisor and once without.