Overview
A under 50 tph crushing plant is a common size for Pakistan. Main machines: small jaw + impact/cone, skid or mobile. Contractor and pilot scale, fast set-up.

Main equipment
- small jaw + impact/cone, skid or mobile
- Shipped to Karachi.
- Configured to 400V 50Hz / PSQCA.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Pakistan
- Port: Karachi.
- Voltage: 400V 50Hz.
- Standards: PSQCA.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 10–50 t/h |
| Typical main line | small jaw + impact/cone, skid or mobile |
| Scale note | Contractor and pilot scale, fast set-up. |
| Destination port | Karachi |
| Site supply | 400V 50Hz |
| Local standards | PSQCA |
| Region | Asia |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | ten-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | strict product cubicity |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Size the primary stage for 10–50 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Pakistan.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Nameplate data for 400V 50Hz and the PSQCA certificate set.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Dust and noise control designed to the local emission limits for Pakistan.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Choke-feed arrangement: surge bin, feeder control and level indication.
Share this list with a small contractor crew as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 49% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Overlooking dust, noise and water permits in Pakistan until erection has already started.
For contract crushing on short-term sites, protect the strict product cubicity requirement explicitly in the contract documents.
Commissioning checklist
- Verify rotation direction on every motor before coupling.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Sample each product fraction and compare with the specification.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Dry-run the plant empty for the specified period and record vibration.
- Test emergency stops, pull wires and interlock trips in sequence.
- Record the baseline grading curve for each product fraction.
The commissioning record becomes the reference for every liner change in the ten-year plan.