Overview
A 200–300 tph crushing plant is a common size for Algeria. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Main equipment
- large jaw + 2× cone + screens
- Shipped to Algiers.
- Configured to 380V 50Hz / NA.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Algeria
- Port: Algiers.
- Voltage: 380V 50Hz.
- Standards: NA.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Destination port | Algiers |
| Site supply | 380V 50Hz |
| Local standards | NA |
| Region | Africa |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Lay out the large jaw + 2× cone + screens arrangement with straight conveyor runs and crane access for liner changes.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Specify motors, starters and documentation for 380V 50Hz and NA before manufacture.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
Shortening this sequence is possible on a confined urban yard, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Whether the quoted t/h is achieved at manufactured-sand production or under ideal laboratory feed.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Wear-part interchangeability across machines in the same circuit.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Closed-side setting range and whether automatic setting regulation is included.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Energy draw in kW and the expected kWh per tonne at the design duty.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at 200–300 t/h, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
For manufactured-sand production, protect the maximum mechanical availability requirement explicitly in the contract documents.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Dry-run the plant empty for the specified period and record vibration.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Measure noise and dust at the operator position against the local limit.
- Calibrate the belt scale and any level probes against a known load.
On a confined urban yard, allow extra time for the dust and noise measurements.